Monday, September 14, 2009

living


living
Originally uploaded by Strawbale house Carterton
Have been busy with organizing and discussing all kinds of stuff and forgot uploading photo's. But here it is - lots of progress and baling almost finished. Expect this to be the last week baling and netting is next.



Sunday, August 23, 2009

Finished wall (almost)

Got something to write about again. The first bales went up last week (20 August). The previous weekend we emptied out the garage and shifted the bales into the new house. This was just under a third of the total bales and should be enough to do the girls bedrooms on the eastern side and the hallway. Pim had a go baling with the builders on friday and together we did some more over the weekend.



Sunday, July 19, 2009

Finished roof - view from east

Some tangible results this week: a completed roof. The builders made lot of progress, despite at times horrible weather. We are very pleased with the result.We also found a home for the polystyrene waste from the roof. It can all go to PolyPalace in Poirirua were it will be recycled into underfloor board insulation. Pretty neat as we had only a small amount of waste until know. With the polystyrene being recycled we are keeping it that way. Not sure what will happen next week but we are getting pretty close to the bales now.



Saturday, July 11, 2009

West facing roof

The last two weeks have been a bit of a challenge. Soon after the arrival of the roof panels (two weeks ago), the builder with help of the manufacturer of the roof panels started installation. However, after a couple of hours they discovered the panels didn't fit and couldn't be made to fit. Apparantly, something had gone wrong during production resulting in the top layer being 1 cm to wide. As a consequence the insulation and bottom layer didn't connect with the next roof panel.
The supplier of the roof responded very well and arrangement for supply of a new roof. The builder also arranged for compensation from the supplier for all additional cost resulting from this.
Although we came to a good arrangement we "lost" a week and with the weather pretty crappy not a lot of progress until early this week.
It was also a logistical challenge (on our driveway) to get the big crane in again and the truck to pick the faulty panels and drop off the new ones. The neighbours must have had an entertaining week.
At the end, the real work started again on Wednesday with putting the roof panels over the carport and bedrooms. The roof supplier provided support for the installation. Yesterday the builders started with the west facing part of the roof.


Saturday, June 27, 2009

roof panels arrive

Another milestone this week with the arrival of the roof panels. The roof panels are of a "sandwich" construction. The outside steel layer, insulation layer and inner ceiling all in a single package. The total thickness is approximate 15 centimeter. The insulation material is polystyreen. Not that "natural" but sometimes a few concessions are necessary. The panels are tailor made and 11 meter or 4.5 meter. It was a bit of a challenge for the truck driver to get his unit down the driveway. Lifting the panels of the truck also required a special framework to make sure the panels didn't brake up in mid-air.

The builders also progressed with placement of the rafters and the framework for the deck. The macrocarpa beams are starting to smell nice too.


Sunday, June 21, 2009

ridgebeam



ridgebeam
Originally uploaded by Strawbale house Carterton
Friday, we reached the highest point with the building. A big crane was hired to lift and place the steel beam spanning the lounge area. The macrocarpa beams for the other parts were also lifted in place. The macrocarpa stud in the kitchen was also placed.


Tuesday, June 9, 2009

A nice winter day

This week some steady progress. The weather has been kind to us and the builders and as a result the framing has gone up for the second floor. It is starting to feel like a house and we are getting a feel for the dimensions. Fingers crossed the weather keeps up and the builders can start with the apex. The ridge beams (see last weeks update) are ready and we are looking forward having them on site.